Users can view key output data (Table 10-2) at any location within their model. Summary data can be viewed once a model simulation has been performed. The summary data can be viewed in a table or with labels.

TABLE 10-2 SINGLE-EVENT SIMULATION SUMMARY DATA

Name Unit Description
NHYD - NHYD
DT hr Simulation Time Step
AREA ha Contribution Area
PKFW m³/s Peak Flow
TP hr Time to Peak
RV mm Runoff Volume
DWF m³/s Dry Weather Flow

TABLE 10-3 SINGLE-EVENT SIMULATION LID DATA

Name Unit Description
Volume Reduction Rate (%) (Runoff Volume In – Runoff Volume Out) / Run off Volume In
Volume of Water for Drawdown (m³) Time taken for maximum volume stored in the LID to empty.
Time of Max Ponding (Hr) Time at which the maximum ponding volume occurs.
Seepage Rate (m/Hr) Seepage rate into native soil.
Calculated Draw-down Time (Hr) Time taken for LID to empty after the duration of the storm event.
Maximum Volume of Storage Used (m³) Maximum volume of water stored in the LID throughout the event.