To create Gantt chart controls and their associated attributes, follow these steps:
- Create Gantt Chart Entity
- Access Entity Properties
- From the Application Tree, navigate to Entities > Entity Designer (double-click to open). It will display the Entity Designer tab and expand the menu bar to show additional options.
- From either the Entity tab or the menu bar, select the Add New Entity option. It will display a set of fields in which you can define the properties of the new entity.
- From the Application Tree, navigate to Entities > Entity Designer (double-click to open). It will display the Entity Designer tab and expand the menu bar to show additional options.
- In the fields of the Entity tab, users can define the properties of the newly created entity.
- In the Name field, provide a name for the entity.
- In the Title field, either specify a custom title for the entity or let the system automatically generate it based on the provided name.
- In the Description field, provide a description for the entity, if needed.
- Create Attributes
- Access Attribute Properties
- Once you have created the entity, select the Add New Attribute option from the Entity tab. It will direct you to the Attribute tab where you can define the properties of the new attribute.
- Once you have created the entity, select the Add New Attribute option from the Entity tab. It will direct you to the Attribute tab where you can define the properties of the new attribute.
- In the fields of the Attribute tab, users can define the properties of the newly created attribute.
- Create Data & Reference Attributes
- Start Date/Time: This attribute is used to capture the start date/time of the task or activity.
- In the Name field, provide a name for the attribute.
- In the Title field, either specify a custom title for the attribute or let the system automatically generate it based on the provided name.
- Choose the Date Field option.
- From the Data Type dropdown, select DateTime (Date with Time).
-
End Date/Time: This attribute is used to capture the end date/time of the task or activity.
- In the Name field, provide a name for the attribute.
- In the Title field, either specify a custom title for the attribute or let the system automatically generate it based on the provided name.
- Choose the Data Field option.
- From the Data Type dropdown, select DateTime (Date with Time).
-
Parent: This attribute is used to reference the Gantt chart entity.
- In the Name field, provide a name for the attribute.
- In the Title field, either specify a custom title for the attribute or let the system automatically generate it based on the provided name.
- Choose the Reference option.
- Click on the
button. It will display the Select Reference window. From the entity section, select [AppName] – [GanttChartEntity]. From the field section, select ID.
- Selecting the reference will redirect to the Attribute tab, where the entity section will display [GanttChartEntity] and the field section will display ID.
- Start Date/Time: This attribute is used to capture the start date/time of the task or activity.
- Once users have created the necessary attributes for the Gantt chart control, the end-result should be along the lines of the following list:
- Create & Design Gantt Chart Form
- Access Form Properties
- From the Application Tree, navigate to Forms > List of Forms (double-click to open). It will display the List of Forms tab and expand the menu bar to show additional options.
- From the menu bar, select the New option. It will display the Form Properties window.
- From the Application Tree, navigate to Forms > List of Forms (double-click to open). It will display the List of Forms tab and expand the menu bar to show additional options.
- In the Form Properties window, users can create a new form for the application.
- In the Name field, provide a name for the form.
- In the Form Entity field, either specify a custom name for the form entity or let the system automatically generate it based on the provided form name.
- From the Entity dropdown, select the Gantt chart entity.
- Click OK and confirm both the prompt to start designing the form and the prompt to create a draft.
- Create & Design Main Form
- Access Form Properties
- From the Application Tree, navigate to Forms > List of Forms (double-click to open). It will display the List of Forms tab and expand the menu bar to show additional options.
- From the menu bar, select the New option. It will display the Form Properties window.
- From the Application Tree, navigate to Forms > List of Forms (double-click to open). It will display the List of Forms tab and expand the menu bar to show additional options.
- In the Form Properties window, users can create a new form for the application.
- In the Name field, provide a name for the form.
- In the Form Entity field, either specify a custom name for the form entity or let the system automatically generate it based on the provided form name.
- Leave the Entity field empty.
- Click OK and confirm the prompt to start designing the form.
- Create Local Attribute
- Access Attribute Properties
- From the Form Designer, navigate to the Form Entity tab.
- Right-click on the form entity and select New Field from the context menu. It will generate a new field below the form entity, which can then be customized and defined to suit the needs of the form.
- From the Form Designer, navigate to the Form Entity tab.
- In the Edit Properties pane, users can define the properties of the newly created attribute.
- In the Name field, provide a name for the attribute.
- In the Title field, either specify a custom title for the attribute or let the system automatically generate it based on the provided name.
- Select the Complex Type checkbox (because the control will reference data from another form).
- Select the Is a List checkbox (because the control will hold multiple instances of the attribute’s value).
- In the Complex Type section, select the Gantt chart entity from which the attribute will reference data.
- Click on the
button to save your changes.
- Configure Gantt Chart Control Binding Properties
- After creating the appropriate attribute, users can return to the Designer tab and define the binding properties for the Gantt chart control.