Introduction
This feature introduces several changes to improve the functionality and the quality of existing work type functionality, as follows:
- The existing “work type” field (which uses a report sorting field) is replaced by a new database field called “work classification”
- It is now possible to link a WBS template to a work classification so that a specific WBS plan is automatically copied to a matter using a particular work classification
- A default WBS template can now be applied to all projects, if desired
Feature management
This feature can be made available to users using Feature management. The feature is call “(evergreen) Work classification”
Workspace > Feature management > (evergreen) Work classification
Work classification form
There is a new form for maintaining work classifications. It also allows a classification to be associated with an active WBS templates
PMA >> Set up >> Project >> Work Classification
Field behaviour
Button | Description |
Work classification ID | Allow User to know Work classification ID, also allow them to Select from the Drop down |
Description | Allow User to update the Description text |
WBS template | Allow user to show the ONLY Active WBS template in Drop down and allow them to Select |
Set up
Default WBS template parameter
If an organisation wants to configure a default WBS template for all matters which don’t have a template assigned to a work classification, this parameter will allow them to do that:
Project Management accounting >> Set up >> Project Management and accounting >> Scheduling
Security
Users must be assigned security privileges before they will be able to view or edit work classifications.
System Administration >> Security >> Security Configuration >> privileges
Field behaviour
Button | Description |
View work classifications | Allow User to View the Work Classification |
Maintain work classifications | Allow User to Maintain the Work Classification |
Work classification on a Project
Work classification is assigned to a project when it is created; the new project quick form has been changed accordingly:
Project Management and accounting >> Projects >> All Projects >> Click on New
Project details screen
The work classification will appear under the “Report Sorting” fast-tab, so that it is adjacent to the current “work type” field (also known as sort field 1):
The Work Classification ID should default on the Reporting and Sorting Fast tab depending on the Creation of Matter; if Work Classification is Blank, then it defaults to the blank Value. In edit mode, the value assigned to the matter can be changed by selecting an item from the drop-down.
Adding a WBS to a project
Once a new project has been created, the WBS will have been automatically assigned, according to the classification used and the template it is associated with. For example, this project relates to civil litigation and so has been assigned the civil litigation WBS template: