The S-curve is a very efficient way of presenting management information for project monitoring. Its graphical representation allows for a clear contrast between deviations from what was planned compared to what was carried out, simultaneously.

It works as follows:

Example of an action plan:

Action 1: 10/03/2022 to 10/14/2022

Action 2: 12/01/2022 to 12/14/2022

This means that the project is scheduled to start in October/2022 and end in December/2022. However, since two points are needed to form a line, the S-curve target line will start one month earlier and end one month later, that is, it will start in September/2022 and end in January/2023. In December/2022, the target line will be 100%, meaning that by the end of that month, the project must already be 100% completed. And in the previous months, there will be values ​​distributed among the months, which are calculated by the system itself.

As for the actual line, in order for it to be formed, it is necessary to enable the % real. field, which is in the side menu > Settings > Actions:

With this field enabled, a % actual must be entered in the action when it is already being executed:

With this, these percentages will generate the actual line of the S Curve with values ​​distributed among the months, which are also calculated by the system:

Note: In Planning and Cancelled actions are not considered in the S-Curve.

Was this helpful?

Yes No
You indicated this topic was not helpful to you ...
Could you please leave a comment telling us why? Thank you!
Thanks for your feedback.