The action schedule uses the following calculation formula to generate the percentage of actions:

=(NumberOfActionsDeterminedBeacon*100)/TotalNumberOfActionsDifferentFromInPlanning

In the example below, the percentage of actions completed (blue beacon) is:

=(2*100)/4
= 50%