Now we already have the installation location of the Monitor * (see Fixing the Monitor)* and the location of the Antenna * (see Fixing the Antenna GPS)*, only missing Pass and Fix you Cables, for this, Analyze the best places and paths on your machinery for this passage and fastening, as well as the necessary clearances for your maneuvers.

Some recommendations and observations:

Power Cables

Having defined the best place for passing and fixing the monitor’s power cable, let’s start its installation.

Step Action
1 Using nylon clamps, temporarily fix the Fuse Holder Cable GPS 12 WAYS AN20, by the way defined, leaving enough slack to be able to connect the eye terminals to the battery terminals.
2 Using nylon clamps, temporarily fix the fuse holder so that it is “standing” to prevent moisture ingress.
3 From inside the cabin, pass the AN23 Power Cable, along the defined path, until the CX-5 Female Rectangular Connector reaches the CX-5 Rectangular Male Connector of the cable that comes from the battery.
4 Using nylon clamps, temporarily fix the Power Cable (AN23) that comes with the monitor to the machinery..
5 To prevent moisture from entering the connector, check that the rubber sealing of the female rectangular connector is securely fastened and in the correct position..
6 connect the C rectangular connectorsX-5 until its mechanical locking and move it to test if it was well “stuck”. Note.: Note that there are male/female mechanical polarizers on the connectors to prevent incorrect assembly..
7 connect the CX-6 and C connectorsX-7 to the Monitor and threaded its cover all the way to prevent moisture and dirt from entering
8 Now pull the cables carefully to eliminate unnecessary slack..
9 If you have excess cable, secure it in the defined location so that it does not disturb your operation..
10 Using nylon cable ties, run through the cables giving the final finish and securing firmly at all necessary points to prevent the cable or connectors from becoming slack.
11 perform the Visual Conference.
12 Now let’s go to the antenna cable GPS.

Antenna coaxial cable

Having defined the best place for passing and fixing the antenna cable, we can begin its installation.

Step Action
1 Starting at the Antenna position, connect the Connector TNC angle of 90º CX-3 into the Antenna and tighten securely to prevent moisture from entering..
2 Pass the AN30 coaxial cable through the desired path, to the position of the Monitor in the cabin.
3 plug in connector CX-3 and threaded its cover to the end to avoid entry of moisture and dirt.
4 Using nylon clamps, temporarily fix the coaxial cable, leaving enough room for maneuvers.
5 Now pull the cable carefully to eliminate unnecessary slack..
6 If you have excess cable, secure it in the defined location so that it does not disturb your operation..
7 Using nylon cable ties, run through the cable giving the final finish and securing firmly at all necessary points to prevent the cable from becoming slack.
8 perform the Visual Conference.