From My Work (FN3 Landing Page)

Recipient Query Tasks is the 2nd grid that displays in FN (under Transfer Tasks). This grid will display all queries for your center that are waiting for a response from you.

To filter for the queries that are counted for CPI, follow these instructions:

  1. Select the filter icon on the Updated column.
  2. Change the top dropdown to Is after for equal to
  3. Use the date picker to select the start of the Previous CPI trimester (see below).
  4. Leave the middle dropdown set to AND
  5. Change the bottom dropdown to Is before for equal to
  6. Use the date picker to select the end of the Previous CPI trimester (see below).
  7. Click Filter.

For US Centers, assessment trimesters are:

  • January 1 – April 30
  • May 1 – August 31
  • September 1 – December 31

For Non-US Centers, assessment trimesters are:

  • March 1 – June 30
  • July 1 – October 31
  • November 1 – February 28
Last modified: Mar 08, 2024