Overview
This report gives detailed information on the selected project split by tasks
It enables a comparison of Budget and Total Revenue, but it also shows Actual, Pending and Total Hours
The report also includes remaining forecast – Estimate To Complete, which together with Total Revenue gives Estimates At Completion.
Finally, the report shows Variance At Completion – the difference between the Budget Amount and Estimate At Completion.
Apart from the drill-through options, which are explained in a separate section of the guide, the Project Status Report provides additional Resource information in the form of a tooltip.
The table below explains each column of the Project Status Report:
Column | Description |
---|---|
Project Name -> Task | Drilling down from Project Name to Task Name and Task ID enables splitting project values to task level. |
Task Name -> Task ID | Task ID corresponding to the Task Name. |
URL | Link to the project in Project Operations. |
Budget Amount | Total budget of the project coming from F&O. |
Actual Hours | Timesheet hours approved by Project Manager. |
Pending Hours | Submitted timesheet hours not yet approved by Project Manager. |
Total Hours | The sum of Actual Hours and Pending Hours. |
Actual Revenue | Revenue based on Actual Hours and Sales Rate. |
Pending Revenue | Revenue based on Pending Hours and Sales Rate. |
Total Revenue | The sum of Actual Revenue and Pending Revenue. |
Estimate To Complete (ETC) | Remaining forecast. |
Estimate At Completion (EAC) | Actualized forecast based on actuals and ETC. |
Variance At Completion | The difference between the Budget Amount and EAC. |
Post your comment on this topic.