Overview

This report gives detailed information on the selected project split by tasks

It enables a comparison of Budget and Total Revenue, but it also shows Actual, Pending and Total Hours

The report also includes remaining forecast – Estimate To Complete, which together with Total Revenue gives Estimates At Completion.
Finally, the report shows Variance At Completion – the difference between the Budget Amount and Estimate At Completion.
Apart from the drill-through options, which are explained in a separate section of the guide, the Project Status Report provides additional Resource information in the form of a tooltip.

The table below explains each column of the Project Status Report:

Column Description
Project Name -> Task Drilling down from Project Name to Task Name and Task ID enables splitting project values to task level.
Task Name -> Task ID Task ID corresponding to the Task Name.
URL Link to the project in Project Operations.
Budget Amount Total budget of the project coming from F&O.
Actual Hours Timesheet hours approved by Project Manager.
Pending Hours Submitted timesheet hours not yet approved by Project Manager.
Total Hours The sum of Actual Hours and Pending Hours.
Actual Revenue Revenue based on Actual Hours and Sales Rate.
Pending Revenue Revenue based on Pending Hours and Sales Rate.
Total Revenue The sum of Actual Revenue and Pending Revenue.
Estimate To Complete (ETC) Remaining forecast.
Estimate At Completion (EAC) Actualized forecast based on actuals and ETC.
Variance At Completion The difference between the Budget Amount and EAC.

Feedback

Was this helpful?

Yes No
You indicated this topic was not helpful to you ...
Could you please leave a comment telling us why? Thank you!
Thanks for your feedback.

Post your comment on this topic.

Post Comment