When reporting an operation as finished, this check mark determines, if the subsequent order routing operation should be moved to

  • Processing (Running)
  • Waiting (Ready)

You may say that at the completion of an order routing step, considers the following operation to be moved and ready for processing at the next routing step.
Or you may say that completion of a production routing operation does not automatically launch the subsequent order operation status “Queuing”, but that this status changes from “Queuing” to “Processing” must be initiated by the operator.

Feedback

Was this helpful?

Yes No
You indicated this topic was not helpful to you ...
Could you please leave a comment telling us why? Thank you!
Thanks for your feedback.

Post your comment on this topic.