How to run Make to Order

NAVEKSA MakeToOrder runs off from BC standard screen – Manufacturing – Released orders

  1. A planner changes the Ending date/time (Due Date) on a production order line.
  1. A new window shows up to let the planner make decisions about directions for the changes as can be seen on the next figure:

  1. By pressing the OK button, the system will calculate a new planned starting Date Time for this production order line, and if there are multiple production order lines “up/down” in the order network, they will be adjusted accordingly with new order start and end dates, as well as adjust required dates for component and capacity allocations.
  2. If this is the first production order line the Production order header due date is also updated.

Please observe that no date changes tak place on the sales order line. This is a communication process to tell sales people if you change a production order due date.

Queue time for the first order routing operation lines in every production order line are recognized in calculations of the start date and start time.

This queue-time allowance is calculated on the basis queue time parameter from the work center / production resource for this first work center.

Remark that order lines at the same levels (parallel production) get the same Ending date/time also.

Reaktion

War das hilfreich?

Ja Nein
You indicated this topic was not helpful to you ...
Could you please leave a comment telling us why? Thank you!
Thanks for your feedback.

Hinterlasse einen Kommentar.

Bitte stellen Sie hier keine Supportanfragen.
NAVEKSA Help desk

Kommentar senden