How it works Overview

Level
The relative BOM level code in the BOM “tree” structure.

Component / operation
Component Item Number or operation number

Component type
Component type can be an Item or a Production BOM itself.
Read the Microsoft documentation for explanation of the component type = Production BOM.

Description
Item description for the component
Vendor/ Center. Supplier/vendor number as indicated on the item card or storage of goods (per location).

BOM / Route quantity
Component quantity for the component

BOM demand
The component demand in total

Component quantity
The component quantity in total.

Vendor / center
Related primary vendor or work center.

Replenishment system
If the item has been purchased, the reordering system is indicated as “Purchase” on the item card. If the item has been manufactured, the reordering system has been indicated as “Manufacturing order” on the item card.
In case the item is transferred from another stock, the reordering system is “Transfer”.

Substitution exists
If the item card indicated a replacement for the component, select it here.

Explode BOM
By clicking this box for a production item, the BOM will explode to the next level. It can be done until there are no more levels.
The idea is that you treat one level at a time. If the solution to the problem is relatively early in course, you do not have to break down the BOM further.

Explode route
By clicking this box for a production item. The Route will explode.

Variant code
This is the standard NAV component variant code if it exists.

Fixed minutes
A field containing the fixed minutes for a specific routing operation.

Variable minutes
A field for the use of the variable minutes for a specific routing operation.

Starting Date
A calculated field for the use of determining expected starting date.

Starting time
A calculated field for the use of determining expected starting time.

Ending date
A calculated field for the use of determining expected delivery date.

Ending Time
A calculated field for the use of determining expected delivery time.

Actual stock
Current physical inventory of the item on the physical location inventory.

Calculated free stock
Calculation of free stock includes all quantity transactions up to and including the requirement date if it is entered or transferred from a planned order.
Note that the different quantities appear only if the delivery date is before or equal to the requirement date.
The calculation is made, possibly per a chosen location, in the following way:
“Current stock” plus “Quantities of all expected receipts” minus quantities of all expected issues minus BOM quantity requiremenents “

Calculated Total stock
The calculation of total stock, all quantities are included, regardless of scheduled consumption/delivery date.
The calculation is made, possibly per chosen location, in the following way:
Current stock” plus “Quantities of all expected receipts” minus quantities of all expected issues minus BOM quantity requirements”

Quantity on purchase order
Quantity in purchase orders specifies the quantity which is open on purchase orders and will be received before the “Requirement date “ if entered.
Appears only if prior to or equal to “Required date” in the header.

Quantity in return receipt
Quantity in Return receipt specifies the quantity which is open and will be retuned before the “Requirement date”, if entered.
Appears only if prior to or equal to “Required date” in the header.

Quantity in return shipment
Quantity in Return Shipment specifies the quantity which is open and will be returned before the “Requirement date”, if entered.
Appears only if prior to or equal to “Required date” in the header.

Quantity on sales order
Quantity on Sales order specifies the quantity which is open and will be delivered before the “Requirement date”, if entered.
Appears only if prior to or equal to “Required date” in the header.

Quantity in service order
Quantity in Service orders specifies the quantity which is open and will be delivered before the “Requirement date”, if entered.
Appears only if prior to or equal to “Required date” in the header.

Quantity in transfer from
Quantity on Transfer order from’ indicates the quantity that is in the transfer order from the location up to and including the “Requirement date”, if entered.
Appears only if prior to or equal to “Required date” in the header.

Quantity in transfer to
Quantity on transfer order specifies the quantity which is open and will be received before the “Requirement date”, if entered.
Appears only if prior to or equal to “Required date” in the header.

Quantity in job
Job quantity is included in the calculations if the item carry a usgae link in the job planning line.

Quantity on production order
Quantity on production order specifies the quantity which is open and will be received before the “requirement date “ if entered.
Appears only if prior to or equal to “Required date” in the header.

Quantity on assembly component
Quantity on Assembly component specifies the quantity which is open and will be delivered before the “Requirement date”, if entered.
Appears only if prior to or equal to “Required date” in the header.

Quantity on Assembly order
Quantity on Assembly orders specifies the quantity which is open and will be delivered before the “Requirement date”, if entered.
Appears only if prior to or equal to “Required date” in the header.

Earliest available (lead time)
This field indicates the earliest delivery time for quantity needed, based on the absence of open orders and therefore this item requirements to be reordered.

Earliest available (Order)
A calculated field for the use of determining expected starting date.

Feedback

Was this helpful?

Yes No
You indicated this topic was not helpful to you ...
Could you please leave a comment telling us why? Thank you!
Thanks for your feedback.

Post your comment on this topic.

Please do not use this for support questions.
Contact our help-desk

Post Comment