In EPC a review date can be set on all objects in order to trigger a review cycle. The review date is automatically calculated based on a review frequency for each object. The review date is now only updated only when a major version is published; no longer the case for minor versions.

Example:
Version published date: 1-June-2020
Review Frequency set to : 1 year

Before the new change, the review date will be set to 1-June-2021 regardless if the process was published as minor or major version
After the new change, the review date will be set to 1-June-2021 only if the process is published as major. If it is published as minor, the review date will be the date of the last major publish plus the review frequency period